The following questions and answers address common inquiries about the York Energy Storage (YES) project — an 858 MW pumped hydro storage facility planned in Chanceford Township, York County, PA.

FAQ Categories

  • About the Project
  • Technology & Comparisons
  • Environmental & Recreation
  • Economic & Community Impact
  • Regulatory Process

About the Project

Is this the same project as Cuffs Run?

Yes. The name was changed to York Energy Storage LLC due to new ownership and a clearer description of its location and function. The name also has a better acronym — YES, a positive step to future energy benefits for the region.

YES's own FERC permit application (P-15332) explicitly acknowledges that the project was previously studied under FERC Preliminary Permit No. 10868-000, filed in 1990 by Mid-Atlantic Energy Engineers under the name "Cuffs Run Pumped Storage." William McMahon, the founder and principal of YES, was also a leader of that original effort. Many of the foundational engineering and geological studies from the 1990s remain available and will be updated shortly.

The site has not changed — what changed are the energy markets. The earlier project was abandoned not because the site was wrong, but because electricity deregulation in the 1990s made the economics temporarily unfavorable. That barrier no longer exists.

How does pumped storage work?

Pumped storage is essentially a giant rechargeable water battery. When electricity demand is low (typically overnight), inexpensive or surplus power is used to pump water from a lower reservoir up to a higher one. When demand peaks — during evenings, hot summer afternoons, or cold winter mornings — that water is released back downhill through turbines to generate electricity on demand.

In the YES project, Lake Clarke (formed by Safe Harbor Dam on the Susquehanna) serves as the lower reservoir. A new upper reservoir would be constructed 450 feet above Lake Clarke. Three reversible 286 MW pump-turbine units housed underground would handle both pumping and generation.

If the upper reservoir starts empty, it takes about 12 hours at approximately 850 MW to fill it; the water can then generate power at full capacity for approximately 10 hours, providing 8,580 megawatt-hours of energy per full cycle.

Is pumped storage an old technology?

The basic principle is proven and mature — pumped storage was first used commercially in Italy and Switzerland in the 1890s and came to the United States in the 1930s. But "old" does not mean "obsolete."

The technology has continued to advance significantly. Modern facilities like YES would use variable-speed reversible pump-turbines, which can adjust their pumping and generation rate in real time to match grid conditions — making them far more flexible than older fixed-speed units.

The U.S. Department of Energy, the International Energy Agency, and the International Hydropower Association all identify pumped storage as a critical technology for the future grid. Over 94% of all long-duration grid-scale energy storage in the world is pumped storage hydropower. Currently in the United States there are 40 active pumped storage plants in operation and many more are planned.

Is the YES project needed? And why now?

The timing is driven by a structural shift in how electricity is generated. Old coal and nuclear plants are retiring across the PJM region. Wind and solar — which now account for the majority of new electricity generation being built — produce power only when the wind blows or the sun shines. Grid operators need large-scale storage to bridge the gap.

York and Lancaster Counties are projected to grow by a combined 12.4% in population in coming decades, according to the Center for Rural Pennsylvania. Growing demand plus retiring baseload generation plus intermittent renewables creates a storage gap that YES is specifically designed to fill.

PJM projects a need of 40,000 megawatts of new peak capacity over the next 20 years — 40 times more than the YES project alone. If that capacity is not filled, it could lead to massive blackouts, brownouts, rationing, and significant economic damage. The market that did not exist in the 1990s now does.

Why is the YES project located here?

Pumped storage is one of the most site-specific energy technologies that exists. It requires two bodies of water at significantly different elevations, adequate reservoir volume, stable geology, and proximity to transmission infrastructure. The YES site meets all of these criteria in an unusually favorable way.

A Chicago-based consulting firm engaged by YES determined that the proposed location is "the best pumped storage site in the eastern United States." The site offers 450 feet of elevation between Lake Clarke and the nearby cliffs, sufficient volume for a 580-acre upper reservoir, solid bedrock for tunneling, and proximity to the PJM transmission grid.

These conditions cannot simply be relocated to another site — the geography either works for pumped storage or it does not.

How big is 858 megawatts of capacity?

858 MW is a substantial fraction of a large nuclear power plant's output. For context, the Peach Bottom Atomic Power Station in York County — one of the largest nuclear plants in the region — generates approximately 2,700 MW total across three units. At 858 MW, the YES project would operate at peak output equivalent to nearly one full Peach Bottom unit.

The project's 10-hour generation cycle produces approximately 8,580 megawatt-hours per full discharge — roughly enough to power 285,000 average Pennsylvania homes for an entire day, or to run the city of Baltimore for nearly two days.

The project's annual generation capacity of 1.5 million megawatt-hours is a meaningful contribution to the PJM grid's overall reliability.

Who is the owner of YES?

York Energy Storage LLC is led by William M. McMahon Jr., a retired power systems engineer based in Reading, Pennsylvania, who founded Entech Engineering. McMahon has been involved in developing the Cuffs Run pumped storage concept since the original 1990 FERC application filed by Mid-Atlantic Energy Engineers.

The company is headquartered in Berks County, Pennsylvania. McMahon's persistence is rooted in technical conviction — he and independent consultants have consistently identified this site as the premier pumped storage location on the East Coast, and he has dedicated decades to understanding the site's engineering potential.

Technology & Comparisons

Is pumped storage better than batteries?

For large-scale, long-duration storage, pumped storage has clear advantages that batteries cannot currently match. The YES project would provide 858 MW of capacity with roughly 10 hours of continuous output, totaling approximately 8,560 MWh per cycle.

To replicate that with lithium-ion batteries today would require an enormous installation with a 10–15 year replacement cycle and substantial fire risk. Pumped storage facilities are engineered to last 50 to 100 years with low operating costs and no degradation over time. Their primary raw materials — concrete, steel, and water — are essentially unlimited and do not depend on global lithium, cobalt, or nickel supply chains.

The U.S. Energy Information Administration confirms that pumped storage accounts for 94% of U.S. grid-scale storage capacity.

Who will provide the turbine-generator equipment?

The YES permit application specifies that the facility would feature three reversible pump-turbine units of 286 MW each, for a combined capacity of 858 MW. These would be housed in an underground powerhouse connected to the reservoirs by a 44-foot-diameter shaft and tunnel that trifurcates into three 20-foot-diameter steel-lined tunnels. All turbine-generators would be new construction and are expected to last 50 years.

Major pumped storage turbine-generator manufacturers operating at this scale globally include Voith, GE Vernova, Andritz Hydro, and Toshiba Energy Systems — all of whom have supplied equipment to comparable facilities in the United States and Europe. Equipment selection and procurement would occur during the detailed engineering phase following any FERC license award.

Are there better alternatives to YES?

There are two commonly cited alternatives to pumped storage: natural gas turbines and batteries — both are normally less economical for this application.

Natural gas turbines are easily sited but must be near large gas supply lines, emit large amounts of smoke and pollutants, have lower efficiency than pumped storage, shorter life cycles, and their costs have risen significantly as global demand increases.

Utility-scale battery storage typically operates at full power for only four hours or less, meaning it cannot replicate 858 MW over 10 continuous hours without tripling the footprint, cost, and material supply chain — which raises its own environmental concerns. Battery systems at this scale require lithium and cobalt mining, have 15–20 year replacement cycles, and pose documented fire and disposal concerns.

Some have pointed to coal mine reclamation sites as alternative pumped storage locations — a legitimate avenue being explored nationally — but no such site in Pennsylvania has been identified as comparable to the YES site's natural elevation differential and proximity to the PJM grid. The grid needs multiple storage solutions; the question is not whether YES is perfect, but whether a site this well-suited should be set aside because better alternatives have not been found yet.

Environmental & Recreation

Is the YES project green?

YES is as green as storage of electricity gets, and the broader energy policy record supports that characterization. The argument that the facility will consume fossil fuel energy is a criticism of the current grid mix, not of pumped storage itself. The same critique applies to every EV, heat pump, and battery charger in Pennsylvania today.

The project is designed to operate for 50+ years as the grid becomes progressively cleaner. Its long-term function is to enable more renewable energy by providing dispatchable backup when wind is calm and the sun has set.

The project does not burn any fuel, produces zero direct emissions during operation, consumes no water (it recycles the same water repeatedly), and replaces the role currently played by fast-dispatch natural gas peaker plants — among the dirtiest generators on the PJM grid. An additional benefit is the removal of some silt from the river that would otherwise be deposited in the Chesapeake Bay.

Will the YES project help or hurt local recreation?

YES expects to keep the Mason-Dixon hiking trail that runs through the slopes of the project open, and will improve it during construction — with the possibility of adding a new trail to the observation level of the proposed upper reservoir.

The project will not interfere with river recreation activities during operational hours. River levels will rise and fall approximately one to three feet over the daily cycle depending on river flow — a change of less than an inch per hour, which is far less than normal wave activity. Fishing activities will not change, and a planned 2,000-foot-long porous dike will prevent fish from being drawn into the intake area.

There will be no recreation facilities in the new upper reservoir, as its level will rise and fall 50 feet daily. The underground powerhouse and tunnels — the project's industrial heart — would be largely invisible from the surface.

Will the YES project hurt fish or fishing?

The project permit application directly addresses this concern, stating the facility "will not affect the water quality in Lake Clarke or the Susquehanna River." The open-loop water recycling system does not consume water or alter downstream flow in the Susquehanna.

YES has committed to studying fish population impacts in Lake Clarke with the intent of minimizing conflicts — a standard requirement in FERC hydropower licensing. The upper reservoir would be a new body of water; its ecological character would evolve over time and be subject to mitigation requirements under the FERC license process. Professional environmental reviews will address these concerns in detail during the licensing phase.

Will the YES project change the appearance of the area? What about noise?

The reservoir and dam will be visible. A 225-foot dam stretching 1.8 miles is a significant structure, and a 580-acre reservoir will change the Cuffs Run watershed above Lake Clarke. The description of the project as "almost invisible to the public" refers specifically to the powerhouse and mechanical components, which are located underground.

On the question of noise: pumped storage facilities operate primarily through water movement and underground machinery. The powerhouse is buried in a cavern beneath the dam, minimizing surface noise. During operations, the most audible activity would be water flowing into or out of the reservoir. This is categorically different from the noise profile of industrial plants, wind turbines, or fossil fuel generation facilities.

Does the YES project hurt the water quality of the Susquehanna River?

The YES permit application addresses this directly: the project "will not affect the water quality in Lake Clarke or the Susquehanna River." The system is open-loop in operation — no chemical inputs are required, and no thermal discharge occurs.

The dam and reservoir construction would involve temporary turbidity and sedimentation impacts during construction, as with any major civil works project, but these would be managed through standard FERC-required environmental controls and monitored throughout the build.

The Susquehanna is already one of the most regulated rivers in the eastern United States, with Safe Harbor, Holtwood, and Conowingo Dams already operating on its lower reaches. The FERC licensing process would require detailed water quality studies and ongoing monitoring conditions as terms of any license issued.

Economic & Community Impact

How many construction or permanent jobs will be created?

The YES permit application projects 300 to 500 jobs during a five-year construction period. Construction jobs in energy infrastructure of this scale are typically union-scale positions in trades such as heavy equipment operation, civil engineering, electrical work, and concrete construction. The project would benefit local manufacturers and the broader supply chain.

The permanent operations staff of 25 to 50 represents skilled, long-term employment in an area that would otherwise see those jobs go elsewhere. Beyond direct employment, the project's tax contributions to York County and the state would support indirect employment across government services.

Will the YES project lower property taxes?

The project will lower taxes for the surrounding community. A $2.3–2.8 billion facility generates substantial property tax revenue for York County, the Red Lion School District, and Chanceford Township — revenue that arrives without the typical cost demands of conventional development.

For example, properties on the proposed project site currently pay about $130,000 per year in property taxes. An early estimate of YES taxes is approximately $30 million per year at current tax rates — a major reduction for local township, school, and county residents. This is a common and well-documented benefit of large energy infrastructure sited in rural areas.

Will the YES project increase or decrease electricity prices?

Grid-scale storage reduces peak electricity prices by displacing expensive fast-dispatch peaker plants — typically older natural gas turbines that run only during high-demand periods and charge premium rates. When pumped storage releases water during a demand spike, it directly suppresses the price spike that would otherwise occur.

PJM Interconnection, which would operate the YES facility's output across its 13-state territory, has documented that storage resources reduce capacity prices and wholesale electricity costs for ratepayers. Over the 50-year life of the project, consumers across the PJM footprint — 60 million people in 13 states — would benefit from the price-moderating effect of dispatchable storage capacity.

Who benefits if the project is not built?

No one. If the YES project is not built, the existing landowners and residents would not be displaced, but they would also not receive generous compensation for their properties and transfer inconvenience.

Beyond that, the calculus becomes increasingly unfavorable: the PJM grid loses a major source of low-cost, dispatchable storage; York and Lancaster Counties lose $2.3 billion in initial economic investment, 300–500 construction jobs over five years, 25–50 high-paying permanent jobs, and much lower property tax revenue for the township, school district, and county.

Manufacturers and businesses across 13 states will continue to face higher peak electricity costs without the price-moderating effect of storage. The renewable energy transition loses a critical enabler — a facility that would allow more wind and solar to be deployed by providing the backup reliability that makes intermittent generation viable.

Regulatory Process

What is a FERC Preliminary Permit? Is it important?

A FERC Preliminary Permit is the formal first step in the federal hydropower licensing process. It grants the applicant priority rights to study a site for pumped storage development for a period of four years (extendable to eight). The Permit is not approval to build — it is permission to invest in the feasibility work required to make a build decision.

YES must use the permit period to raise approximately $12.5 million and complete environmental, engineering, geological, and economic studies. Only after those studies are completed can the company decide whether to apply for a full FERC license. That license application would trigger a comprehensive environmental review process involving federal and state agencies, public comment periods, and potential hearings.

FERC granted the preliminary permit to YES in November 2024 after reviewing the application and determining the project merited further study.

Sources: York Energy Storage LLC FERC Permit Application P-15332 (Jan. 2024); U.S. Department of Energy pumped storage resources; International Energy Agency Grid-Scale Storage report; U.S. Energy Information Administration; International Hydropower Association; FOX43; Philadelphia Inquirer; One United Lancaster; ABC27; LancasterOnline; Grid Magazine; Lark Scientific energy storage comparison; NREL Annual Technology Baseline 2023; Center for Rural Pennsylvania population projections.